Wednesday, November 22, 2023

Report and recommendations on the GLOF disaster which affected Teesta valley in Oct2023.

We, in the Darjeeling Himalaya Initiative (DHI) submitted a report (with recommendations)  to the NDMA and the SDMA’s of W Bengal and Sikkim based on our observations and interactions with affected people in the numerous visits to GLOF affected areas between 27th mile, Kalimpong District, W Bengal and Dikchu in Gangtok district, Sikkim more than a week ago. The reports were substantiated by the many posts and photographic records on the disaster made in the SaveTheHills blog.

Having visited some of the worst affected areas in North Sikkim between 17-19Nov2023, we can only reaffirm what has been reported:

  • We need an expert team to visit these areas and advise us the course of action to be taken in the limited time we have before the next monsoons.
  • That we should focus on building the resilience of communities in the flood affected areas while continuing with the recovery and reconstruction process, since many of our populated areas in the Teesta Valley in Sikkim and W Bengal will again be affected during the Monsoons 2024.
  • That time is of essence.
The full report is reproduced below:

Report and recommendations on Glacial Lake Outburst Flood (GLOF) affected areas between Dikchu (Sikkim) and Teesta Low Dam Project III (TLDP III, 27th mile), Kalimpong (West Bengal)

Report Drafted by SaveTheHills

Submitted by SaveTheHills and Darjeeling Himalaya Initiative
Reported areas are in RED circles

  • What we people living along the Teesta valley in parts of Sikkim and Kalimpong District of West Bengal, witnessed in the early hours of 04Oct2023 was a rare, dangerous and a huge catastrophe with the Glacial Lake Outburst Flood (GLOF) from South Lhonak Glacier, massive dam breach at Chungthang and subsequent floods causing loss of life and livelihoods and devastating large areas of the valley. The size and scale of the event has far escaped the appropriate attention of both the national and concerned state governments. It has been totally under reported by the mainstream media. Many of us, even from Darjeeling and Sikkim Himalaya have pushed it to distant memories and forgotten that there is massive work ahead with rehabilitation and mitigation.

  • When the very turbulent waters of the GLOF from South Lhonak glacier located at 17,300 feet above mean sea level crashed into the already brimming reservoir of the 1200MW Sikkim Urja Dam at Chungthang, the dam was quickly overwhelmed and burst, releasing a wall of water which was 10-15 feet high. This deluge swept through the Teesta valley, destroying everything in its 162 km rampage from the glacier to NHPC Teesta Low Dam Project (TLDP) III at 27th Mile in Kalimpong district.
  • This report is an attempt to preserve facts of this humongous event and to urge both government and civil society to recognize and respect the vulnerable fragility of the Himalaya. It is extremely apparent that there is the need to be prepared for more such disasters as the Himalaya gets warmer.
  • The fundamental recommendations stem from extensive field visits to GLOF affected regions and in-depth conversations with the affected residents. Having witnessed the profound impact of this catastrophic event on infrastructure and communities, it is crucial to recognize that we have a mere five-month window to initiate remedial actions. Our primary objective is to empower and ready the traumatized community to confront the challenges of the upcoming monsoon season in 2024, ensuring improved safety and resilience, and safer road networks for the thousands who transit each day.
  • We have not visited Chungthang and other affected areas in North Sikkim as yet, but have made several visits to GLOF affected areas between Dikchu and 27th Mile (Kalimpong district) and photo essays from our visits are placed in the STH blog http://savethehills.blogspot.com.
  • It is requested that this report be read in conjunction with more specific inputs from our photo essays in the STH blog which will amplify the observations that are made below.

    Teesta river in spate at the Teesta bridge, on 04Oct2023 (drone image)

Observations

The Teesta river 

  • The Teesta is still unusually large and fast for this time of year. As such it is continuously eroding sections of NH10 as well as low lying populated areas like the Teesta bazar.
  • The river level, post GLOF is much higher; undoubtedly due to the silt deposits as the river slows down in areas of less gradient. In this regard, Mr Lalitendu Tripathi, Executive Director, NHPC, (North Bengal and Sikkim) stated in an interview with a local TV channel ‘Himal World’ that the level of the whole Teesta Basin had increased by 3-4m due to the debris deposits.
  • Locals blame the huge silt deposits by the Teesta on the IRCON project and the tunnel excavations which were dumped on the river banks and which were swept away by the GLOF. To make matters worse, the sludge and sand that is being excavated from all areas as communities try to rehabilitate is being dumped back into the river or onto the river bank. This will undoubtedly increase the silting of the river and increase the river levels even further.
  • Many of the affected people interviewed stated the river was ‘far away and far lower’ before the GLOF event. As such, Teesta at many places is now flowing in the vicinity of populated areas, some of which are subsiding.
  • The amount of debris which has been brought down by the GLOF is phenomenal and besides tree trunks and branches which are visible and strewn all over the river banks, the invisible heavier debris would also include metal from the many bridges swept away, vehicles, boulders and parts of homes which must be buried deeper in the sand and also ammunition and explosives which make the task of clearing the debris risky.
  • The thickness of the silt/sludge deposits on the river bank, roads or burying homes is 10 feet or more.

Early warning mechanism

  • The media is fuzzy whether an AWS (Automatic Weather System) or a GLOF EWS (Early Warning System) was available in North Sikkim but whatever was installed, failed to work.

    What worked was a much more primitive system where alerts were sounded on bull horns, doors were banged, whistles blown and people informed on cell phones that ‘the river had become big’ and they should move to higher ground. At places the police force was very effective but in the end it was just people reaching out to each other, to their friends and relatives downstream which resulted in less casualties.
    All this took place when our entire region was being pelted by heavy rain, in pitch dark in the early morning hours on 04Oct2023. It was fortunate that the cell phone system worked otherwise there would have been far more fatalities.

Impact on communities and settlements

 

  • We talked to numerous GLOF affected people in Sikkim, as well as in Kalimpong district. Everyone unanimously said they were scared of living in their present homes and requested the government or political party to relocate them to a ‘safer place’.

  • Many homes in the shanty /slum areas were swept away by the GLOF (IBM colony – Rangpo, below the Melli bridge, at Teesta Bazar, Geil Khola and Bangay bazar.) Displaced residents from here are living in relief camps or with relatives in Kalimpong district (W. Bengal). Affected people from Sikkim were given compensation by the government on 26Oct2023and have returned home – relief camps in Sikkim have been closed.
  • Many of the RCC homes survived the floods but were buried under a 10-15 feet blanket of sand and sludge. The owners of these homes are excavating their homes and returning.
  • Some parts of Teesta bazar which are on the river bank are subsiding due to the erosion of the river which is now flowing very close to these areas.
  • Many buildings and homes adjoining the river banks have now been weakened with large cracks and their foundations eroded.
  • Many concrete homes (which were not washed away) are still submerged in water at places.

Impact on the roads, NH10 (Singtam to TLDP III section) and bridges

  • Parts of the Teesta to Darjeeling road was under water until 20Oct2023. This road and
    NH10 were opened for light vehicle traffic only and between 6am-6pm, on 21Oct2023.
  • Due to the restriction in heavy vehicles using NH10, all the heavy vehicle traffic from Sikkim and Kalimpong is now being routed thru the Lava - Gorubathan route. This is causing severe traffic jams in certain areas as well as disturbance to residents of Kalimpong, Pedong and Lava since the traffic is only allowed to operate at night. This route from Kalimpong to Siliguri is also much longer and takes 7 hours whereas the NH10 route only takes 3 hours Consequently, this detour directly affects the availability and cost of goods in Kalimpong and Sikkim.
  • With the river level much higher now, it flows almost at the same level as the Teesta – Darjeeling road.
  • When checked on 02Nov2023, parts of Teesta bazar – Tribeni road were still submerged under the Teesta river.
  • NH10 has been damaged severely at many low lying areas where the Teesta flows close to the road. In such areas, the edges of the road are cracked and the river continues to pull down chunks of the road making driving on this road a risky proposal (hence the timings for use of the road and restrictions on heavy vehicles). Examples of such areas on NH10 are

     - Directly opposite Melli bazar
- From Teesta bazar to Baluakhani (TLDP III) towards Siliguri.

  • While the 29th Mile landslide near Teesta bazar remained stable during the GLOF, a very old landslide which had been dormant for decades was activated at Likhu Bhir.
  • Many sections of NH10 are subsiding into the river.

  • Major bridges (in the area surveyed) which were destroyed by the GLOF were Indreni bridge linking Singtam with Adarsh gaon and NHPC bridge from Tar Khola to the Patel Engineering Complex in Sikkim.

 Condition of the dams and economic impact.

  • Sikkim – Urja dam Stage III has been destroyed.
  • The NHPC dam at Dikchu (Stage V) has also been severely damaged by the GLOF and as per the Executive Director (NHPC), Mr Lalitendu Tripathi it would take a year to restore operations.
  • NHPC Stage VI dam at Sirwani (Sikkim) had a huge amount of debris dumped into it and the under construction power station for this dam at Tar Khola (with Patel Eng.) was almost wiped out.
  • We do not know the condition of TLDP III fully. However, the 3-4m siltation deposit on the riverbed and repair of some damaged mechanical parts will prove a challenge here. Moreover, filling the reservoir will probably flood parts of Teesta bazar, the Teesta - Darjeeling road and the Teesta -Tribeni road.
  • As on date no major dam has been functioning in the Teesta valley from 04Oct2023, upto and including TLDP III.
  • The economic impact though not exactly known is huge and much of it is being claimed from insurance. The complete socio-ecological loss of the disaster is incomprehensible and not easily monetized.

Impact on areas not surveyed

  • Our surveys thus far have been confined to urban areas and accessible roads, limiting our assessment of the situation. The catastrophic impact of the GLOF plus dam burst is starkly evident in the extensive damage inflicted on forests, as millions of uprooted trees now litter the riverbanks.
  • The vulnerability of these remote, less-accessible areas needs to be assessed as we anticipate the upcoming monsoon season

Recommendations

1. Detailed Assessment of the GLOF impact and its future repercussion

An expert committee needs to be set up urgently to look into:

  • High river levels, likely flow pattern of the river and vulnerability of populated areas in the proximity of the river in the next monsoons.
  • Assessment of condition of NH10 and other roads in areas impacted by GLOF. As on date, many places between Likhu Bhir and 27th Mile and around Melli show signs of subsidence.
  • Alternate routes for heavy and light vehicles, timings for use of roads and traffic control in such areas need to be planned and informed to the public.
  • Vulnerability of sinking populated areas such as those in Teesta bazar and other places needs to be studied and mitigation methods such as protective embankments implemented.

2. Rehabilitation of affected homeless people

  • Rehabilitation is an extremely traumatic and distressing experience for people affected by disaster where they have to uproot themselves from their homes and relocate to a strange, different place and adapt to an entirely different environment.
  • The GLOF event has resulted in many people whose homes have been swept away and their place of residence has become too dangerous to live in and as such today temporarily live in relief camps or with relatives or in rented places. The number of such people will increase in the future as more areas get affected by the Teesta river.
  • Relocation of such people needs to be planned and looked into and safety, opportunities and well being factored into the rehabilitation process.

3. Strengthen preparedness

  • A fail safe Early Warning and Dissemination System needs to be provided in the vulnerable areas of Teesta Valley.This should be a system which will continue to function in a disaster scenario with severe power outages and damage to cell phone towers - which is likely to happen in a major disaster.
  • Manual hooters and other disaster alerting systems should have a distinct sound which cannot be confused with ambulance or other siren sounds.
  • The status of NH10 and other prominent roads must be informed to the public through social media or electronic sign boards at key places.
  • Relief centres in vulnerable areas should be planned in advance so that they could be set up rapidly in the event of a disaster. Solar lighting/ generators must be provided in such places.
  • The cell phone system in the Teesta valley played a crucial role in saving numerous lives and ensuring continuous communication with affected individuals during the recent disaster. However, given the susceptibility of this communication system to landslides and power outages, it is imperative to establish a resilient backup solution. Implementing ham radios as a back-up communication may be considered. These ham radios can be operated by ex-servicemen, who are already trained to operate such equipment.
  • Investment in power rescue tools, solar lighting, first aid training, home insurance, AWS (automatic weather stations), etc. all would be immensely helpful in building a more resilient community.

4. Capacity building and raising awareness.

  • Massive awareness campaign along with CBDRM needs to be implemented. Many lives were lost when people chose to ignore the warning issued either on the cell phone or in person.
  • Periodic evacuation drills need to be conducted in all vulnerable areas.
  • Capacity building for communities in the valley has to be a priority action. Their experiences of what worked during the disaster therefore needs to be strengthened. What were the gaps needs to be studied, improved and documented. Serious efforts must be made for working on the gaps in a time bound manner, with constant monitoring mechanisms put in place.
  • A ‘Lest we forget’ memorial can be made by preserving any of the structures that have been impacted by the floods. This can be developed into a good awareness and educational space for people to visit with interpretation material that consist of write ups / photographs / human stories on the event of October 4th 2023.

Conclusion

As has been stated already, the Oct2023 disaster is the most serious disaster to have affected the Darjeeling -Sikkim Himalaya after the October 1968 deluge. It has not received due attention because its greatest impact was confined to the Teesta valley that does not always take center stage. Also the number of fatalities was comparatively limited and disaster discourse does not fully acknowledge the socio-ecological importance of the mountains and the cumulative loss due to disasters. The impacts of the GLOF, dam breach and subsequent impacts on infrastructure and urban settlements cannot be understated and needs to be looked into with urgency and importance. Time is of essence, with the monsoons of 2024 just months away. We urge experts to visit and assess the situation and remedial action to be initiated without delay so that the impacts of this disaster do not continue into the coming monsoon.

Wednesday, November 15, 2023

Photographic record of the impact of 04Oct2023 GLOF at Melli bazar and its vicinity -13Nov2023


Melli (27 05 24.2 N 88 27 29.6 E) Elev 232.9m, is a place which straddles the Teesta river. In South Sikkim, it is a small town, whereas in W Bengal (Kalimpong district) it is a transit place on NH10, Kalimpong district ,W Bengal.
We visited Melli during our survey of Teesta bazar on 10Oct2023 but could not access Melli (Sikkim) because the road from the bridge to the Melli town was closed to traffic.
On 13Nov2023, more than a month after the GLOF event I could make it to Melli town (Sikkim) with Prof Malay Mukul (Dept of Earth Sciences, IIT Bombay). Malay is from Kalimpong and was on a brief vacation here. These are some images from our visit on 10Oct2023:
Drone image (by Praveen) of the Melli ground  and stadium with the Teesta river nudging the edges of the complex.
Shredded parts of NH10 with a view of Melli town (Sikkim) from the opposite bank.
An excavator had started removing sand and sludge from the stadium on 10Oct2023.

Images from our visit on 13Nov2023 to Melli.
A dumper at the Melli ground belonging to SML company had been excavated along with the first floor of the several buildings at the rear.
The wreckage of another vehicle lay at the edge of the Melli stadium. Excavation of the sand, debris and sludge was continuing but seemed a humongous task considering the almost 10-15feet of sand that was dumped everywhere. Prof Malay Mukul can be seen in the background taking some readings.
Another view of the Melli stadium with buried vehicles strewn all over. Notice how close the river had come to the main town during the GLOF. In the distance and across the river is the IRCON railway tunnel.
This was the area which was most affected in Melli town (Sikkim) by the GLOF event.
A sombre Milan Gurung (48yrs) stands at his home near the Melli stadium with the Teesta river lapping up the edges of what used to be his front yard. He told us that 3 new vehicles from SML company were swept away here along with a large liquor storehouse.
He squarely blames the inundation of his home on the dumping of excavated tunnel material on the opposite bank by the IRCON project. He says the river first hit the huge IRCON debris on the opposite bank and rebounded from it, to flood his home and 10 houses around the stadium.
Milan Gurung told us the river was never so close to his home earlier and was fearful about living here now.
Debris at the opposite end of the stadium.
Residents of this area said the sewage treatment plant of Melli town was located here and it was either swept away or buried.
Dangerously poised GLOF affected buildings on the W Bengal side of Melli Bazar.
The problem is that there are so many weakened structures like these, everywhere with the river nibbling away at the base.

Images of Tribeni (at the junction of Rangeet and Teesta rivers)

Image of the GTA Covid Hospital at Tribeni on 10Oct2023.
Image of the GTA Covid Hospital at Tribeni on 13Nov2023.
Rangeet river water is distinctly green whereas that of the Teesta is still laden with silt and brown.
Road to GTA Covid Hospital at Tribeni on 13Nov2023
A large section of road (approx 300m) from Teesta bazar  to the GTA Covid Hospital at Tribeni is still submerged - with the river having regained its lost territory.
The river submerges the road here (27 04 6.8 N 88 25 39.7 E) just 10 mins walk from the Teesta bazar. Sadly, this place has now become a dumping ground for solid waste.

The road remains under water for a long time until it reaches here (27 04 14.4 N 88 25 49.2 E) where it climbs out of the river.

My thanks to Prof Malay Mukul for taking time off to visit these places. I will update his inputs in a separate blogpost.

Praful Rao
Kalimpong district
Darjeeling-Sikkim Himalaya
savethehills@gmail.com
9475033744



Sunday, November 12, 2023

Cyclone Aila (26May2009) vs GLOF (04Oct2023) : Photos of Teesta river at Teesta Bazar

Cyclone AILA was a huge disaster event which impacted Darjeeling- Kalimpong districts between 24May and 26May2009 when it dumped 247mm of rain in Darjeeling in 24hrs. 17 people lost their lives in the storm. STH tracked the cyclone and has blogged extensively about it in May and June2009. (See 1, 2, 3).

In order to understand the magnitude of both these disaster events I have placed photos of the impact on the Teesta river, taken from approximately the same location on the Teesta bridge in May2009 and in Oct2023.

Photos of the Teesta river of 2009 were courtesy Mr Naren Tamang of Kalimpong TV and taken DURING the storm - please note no major dams were operating upstream in the Teesta valley then.

Photos of the GLOF event were taken by me on 10Oct2023, 6 days after the the GLOF event.

Cyclone AILA (26May2009): Photo of homes close to the river bank almost directly below the Teesta bridge. The Teesta - Darjeeling road is intact and was not touched by the river during Cyclone AILA.
GLOF (10Oct2023): Image of almost the same area, 6 days after the GLOF event. Note the level of the river vis-a-vis the level of Teesta -Darjeeling road.
Cyclone AILA (26May2009): Teesta river (looking north). No major dams were operating then and settlements of Teesta bazar near or on the bank were minimal.
GLOF (10Oct2023): Teesta river (looking north). Almost the same scene but 14 years later. Note the density of the settlements on the river bank - many such homes were swept away
Cyclone AILA (26May2009): Photo of Teesta from the bridge (looking south). The Teesta to Darjeeling road (extreme right) is considerably higher than the river and was not damaged by AILA.
GLOF (10Oct2023): Photo of Teesta from the bridge (looking south).The level of the Teesta is so much higher and parts of the Teesta to Darjeeling road are under water.

Praful Rao
Kalimpong district
Darjeeling-Sikkim Himalaya
savethehills@gmail.com
9475033744

Thanks to Naren bhai for the images of Cyclone AILA




Saturday, November 4, 2023

Photographic record (Part II) of the impact of GLOF on parts of Teesta valley between Tar Khola and Dikchu - 22Oct2023

This blog (Part II) covers our visit from Rangpo to Dikchu.

Rangpo (27 10 28.7 N 88 31 23.6 E) Elev: 312.6m
We first visited Rangpo, a major town in SIkkim which was severely affected by the GLOF, on 06Oct2023 and reported on it here

When we visited Rangpo on 29Oct (on our way to Dikchu) after our first visit there on 06Oct2023, much had changed. The town, where the GLOF had blanketed 438 buildings in the IBM market place with a 10 feet layer of sludge (while sweeping away 128 lighter structures) was in recovery mode. There was a continuous drone and clank of heavy machinery as excavators dug out sludge and huge trucks ferried the debris away.

Placed below are several photos of approximately the same area, taken on 06Oct (Top photo) and on 29Oct2023.


Overlooking the main town across the Rangpo river, excavation work continues on the W Bengal side of Rangpo on 29Oct2023. (Photo credit: Praveen)

Singtam (27 13 42.5 N  88 29 34.6 E) Elev: 347m

Singtam is the business hub centre of Sikkim with much of the supplies going thru this town. The GLOF of 04Oct2023 caused severe and extensive damage in the Singtam region (Adarsh Gaon, Lal Bazar and Goli Tar). 
Adarsh Gaon (see photo of 21Aug2019 above) always had a history of flirting with floods because it is located on the banks of the Teesta. Residents of this place squarely blamed dam operations as the cause of the periodic flooding which takes place here.
Adarsh Gaon after the GLOF. The level of the flood waters can be clearly seen as can be noticed the sand being removed from the apartments where the river entered.
The Indreni bridge connecting Singtam (Lal Bazar) to Adrash Gaon during happier times.
Where Indreni bridge once stood. The savagery of the floodwaters is evident from the steel rods of the supporting pillar which have been ripped off and bent. (Lal bazar, Singtam)

This mangled remains of Indreni bridge has been swept almost 200m downstream by the GLOF
Clean up and excavation operations in progress at Goli Tar, Singtam. As per a panchayat representative, 56 homes were severely damaged by the GLOF here but heeding to the alert from friends and the police, people rushed upto the 'hospital area' - as such there was no loss of life.(Drone image by Praveen)
A severely damaged home at Goli Tar, SIngtam.
At all affected places, we observed a frantic effort by people to get their lives back to normalcy. Heavy machines were continuously dredging out sand, dump trucks ferrying it to the river bank and people tirelessly shoveling out sludge from their homes. Here a temple is being excavated at Goli Tar, Singtam.
Vehicles which were excavated from the river at Goli Tar, Singtam. A person I talked to  reported seeing vehicles with headlights 'ON' floating down a wall of water at 3am.
Damaged heavy electrical equipment at Goli Tar, Singtam.
Three weeks after the GLOF of Oct2023, the flood waters had still not dried out in some shops in Lal Bazar, SIngtam. As per a panchayat official, more than 120 houses/shops were severely damaged by the GLOF event in Lal Bazar, while 30 houses were totally washed away by the river.
Literally picking up pieces of their lives, traders in Lal Bazar, salvage whatever they can from their shop which the GLOF engulfed.
Sludge being dug out from heavily populated business areas of Singtam, Sikkim on 29Oct2023
DIkchu NHPC Teesta Stage V dam and Dikchu town (27 23 12.0 N  88 30 18.0 E) Elev: 591.8m

The Teesta Stage V dam at Dikchu is the first major dam after the Sikkim Urja dam (Stage III) at Chungthang (Elevation: 5500')
The Stage V Dikchu dam (elevation 1940') is approx 33km from Chungthang and located in a steep, narrow rocky gorge.
NHPC Dikchu Stage V (510 MW) dam on 09Jan2023 (Photo credit: Praveen)
Drone image on 29Oct2023 (Photo credit: Praveen)
Another view of NHPC Dikchu Stage V (510 MW) dam on 27Mar2023 when we visited Dikchu town to investigate a landslide.
Look carefully and you will notice which structures at the dam site were damaged by the GLOF on 04Oct2023 in the following photos.👇
Blocked tunnels located a short distance downstream from the dam along the river bank.
Teesta river and the Stage V dam at Dikchu on 29Oct2023.
Stage V dam at Dikchu on 29Oct2023.
Stage V dam at Dikchu on 29Oct2023.
The Control Gates on top of the dam which had been opened apparently before the GLOF ; all three had a huge amount of debris strewn all over and around them.
Large tree trunks, sludge and other debris around this structure which is on top of the dam.
Two of the 3 control gates of the dam. All three were open but covered with unimaginable debris and sand.
This appears to be some electrical component of the dam which was severely damaged if not destroyed. It is on top of the dam and visible in our photo of 27Mar2023.
Sludge, tree stumps and roots, damaged or destroyed components, all on top of the dam, dumped by the Teesta river as it flowed over the dam for some time during the early morning hours of 04Oct2023.

Clearly, dams and particularly NHPC took a big hit during the GLOF of 04Oct2023.

Dikchu town (27 24 4.1 N 88 31 12.1 E) Elev: 599.6m
This was the last place we visited on our survey on 29Oct2023. 
Here several buildings and homes crumbled under the impact of the surging waters of the Teesta and a school ground and a temple was destroyed below the town. They received messages from their relatives and friends at around 12.30am on 04Oct2023 that 'the river was coming' and again they evacuated in pouring rain to a school located on higher ground and in pitch dark. Several Border Roads Organization personnel who were staying on rented home also lost everything as they moved to safer places at night. Many homes are cracked and unsafe in the town as per locals.
A home which slid down as the river gnawed the base of the hill. This is in the centre of Dikchu town. Do note how precarious it has become for other homes on the edge.
A new building which was still under construction rolled over as the Teesta river eroded the base. The river is still very close to Dikchu town.

A brief note and a reminder

Today, 04Nov2023 is exactly one month since South Lhonak lake, in the high Himalayas burst its banks and caused a GLOF. It was a mammoth and hopefully a rare event where a GLOF triggered a major dam burst which destroyed the lives and livelihoods of so many in our region. The economic cost also has been huge. Unfortunately, neither mainstream media nor our governments thought much of the event, which is another reason for worry - since we are all back to business as usual with highways cracked, parts of towns dangerously weakened, the Teesta flowing at a higher level and closer to many populated areas and so on.
And the next monsoons just 5 months away.
And things are changing on the ground too. After one month of clear, sunny weather (and onset of  the festive season), the rivers are mercifully shrinking, the repairs are on, relief centres in Sikkim have been closed and affected people in Sikkim and Kalimpong district are trying to get on with their lives.
With this blog, we have tried to capture quickly all that happened in photographs before everything changes and we forget what was truly a major disaster in the Darjeeling- Sikkim Himalaya. Thus far we have covered only a small part of the affected areas between 27th Mile, Kalimpong district, W Bengal to Dikchu town in Sikkim and even that we have done very cursorily due to time and other constraints.
We will try to cover affected areas upto Chungthang before severe winter sets in.
My thanks to all the affected people who talked to us and we hope our photo essays on this event will help them in some way.

Praful Rao
Kalimpong district
Darjeeling-Sikkim Himalaya
savethehills@gmail.com
with
Praveen Chhetri
Junkeri Studios
9733185815